Progress

October 28, 2020 – Our high school group hosted the final event held in the Chapel

November 2, 2020 – Abatement begins, prior to demolition

December 7, 2020 – Demolition start

January- February, 2021 – Basement Dig

March – May, 2021 – Basement footing and wall rebar installation, underground plumbing

June 2021 – Foundation concrete pour, basement wall fabrication

June, 2021 – Basement dirt backfill, first floor preliminary work

July, 2021 – Basement steel and decking installation

July, 2021 – First floor pad prepared

August, 2021 – Exterior wall framing and second floor decking

September, 2021 – First floor foundation and concrete slab pour

November, 2021 – Framing begins

January, 2022 – Exterior dens glass installed (walls)

February, 2022 – HVAC, electrical, fire systems installed

March, 2022 – Interior drywall installed, roof complete

Late September, 2022 – Anticipated Completion