October 28, 2020 – Our high school group hosted the final event held in the Chapel
November 2, 2020 – Abatement begins, prior to demolition
December 7, 2020 – Demolition start
January- February, 2021 – Basement Dig
March – May, 2021 – Basement footing and wall rebar installation, underground plumbing
June 2021 – Foundation concrete pour, basement wall fabrication
June, 2021 – Basement dirt backfill, first floor preliminary work
July, 2021 – Basement steel and decking installation
July, 2021 – First floor pad prepared
August, 2021 – Exterior wall framing and second floor decking
September, 2021 – First floor foundation and concrete slab pour
November, 2021 – Framing begins
January, 2022 – Exterior dens glass installed (walls)
February, 2022 – HVAC, electrical, fire systems installed
March, 2022 – Interior drywall installed, roof complete
Late September, 2022 – Anticipated Completion